Construction could begin in 2027, starting Panamá–Capira

20 April 2026 · Source: Newsroom Panama ↗
Construction could begin in 2027, starting Panamá–Capira

With feasibility studies underway, the SNDF indicated the tender for the first section, Panamá City to Capira, could open in 2027. That first stage is projected to take at least five years.

Background & context

This is the earliest official date attached to an actual tender, and it's narrower than headlines suggested: only the Panamá City–Capira segment, only a tender opening (not construction starting) in 2027, and even that is explicitly conditional on the feasibility studies due weeks later.

The five-year estimate for this first stage alone signals how large the full 475 km line's timeline really is, if Phase 1 alone takes five years, the seven-to-eight-year full-build estimate implies later phases running in parallel, not sequentially. Read "2027" as the earliest defensible date under the current study schedule, not a promise.

Source: Newsroom Panama ↗
This is an independent summary by Lin Long Projects of publicly reported facts, based on the source above. Always confirm figures and quotes against the primary source before republishing.